Lindenhurst Canal Bulkhead: Which Village, State and Federal Permits Apply to Replacing One

October 23, 2026, updated · Danielle Sandella and Kim Fontanez, Licensed Real Estate Salespersons

A bulkhead is the wall that holds a canal-front yard in place, and replacing one can involve a village, a state agency and a federal agency at once. Here is what each office's published rules say, for Lindenhurst homes on the water.

TL;DR

  • The Village Building Inspector issues building permits for construction or alteration of any structure, "including waterfront structures."
  • The State's tidal wetlands program lists bulkheads among the structures it regulates, and a general permit, GP-1-22-001, covers some replacements in Nassau and Suffolk.
  • The U.S. Army Corps of Engineers requires a Section 10 permit for work in navigable waters, which typically include tidal waters.
  • A general permit applies only to a functional, lawfully existing bulkhead, and no work is authorized until DEC signs the authorization.
  • Buyers and sellers can ask for the paperwork on bulkheads, docks and decks before a contract is signed.

Table of contents

  • Who reviews a canal bulkhead
  • The Village building permit
  • The State tidal wetlands permit
  • The federal Corps permit
  • What a general permit does not cover
  • Questions for the paperwork
  • Lindenhurst in our work
  • Related pages

Who reviews a canal bulkhead

Three levels can apply to the same job: the Village, DEC and the Corps. DEC says the Corps "also has jurisdiction and a Corps Permit may be required whether or not DEC requires one," per its tidal wetlands page. The Town of Babylon's building permit page lists a separate "Bulkheading Building Permit," so the municipality that issues the permit depends on where the address sits, and the Village Building Department can confirm that.

The Village building permit

Section 193-123 of the Village code says that before construction or alteration of any structure, "including waterfront structures," the owner submits an application to the Building Inspector with plans and drawings as required. The Village's permit requirements sheet lists a survey dated within five years, legible plans, photographs of the property, proof of workers' compensation and disability insurance, and a $25 non-refundable filing fee. It also says a property in saltwater wetlands needs a DEC permit, with a copy submitted alongside the building permit application, and that the fee is doubled for legalizing existing structures.

The Village's stormwater chapter exempts "refacing existing bulkheading, but not new bulkheading" from its review.

The State tidal wetlands permit

DEC's tidal wetlands page says adjacent areas extend up to 300 feet inland from the wetland boundary, and it lists "Bulkheads, sea walls, retaining walls, rip-rap, and gabions" among regulated structures. Its GP-1-22-001 page says the general permit allows replacing functional and lawfully existing bulkheads in place or landward, re-sheathing with no more than a 4-inch seaward extension for timber or 8 inches for corrugated material, a replacement up to 18 inches higher, or more where the local FEMA flood elevation justifies it, and limited maintenance dredging.

The request needs a site location map, plans with a survey showing the existing bulkhead, three color photographs and a Permission to Inspect form. The page states that "No work is authorized until the permittee receives the signed Project Authorization by NYSDEC."

The federal Corps permit

The Corps' permit page says a Section 10 permit is required for work or structures in, over or under navigable waters, which typically include tidal waters. It describes Nationwide Permits as general permits for minor projects, with special conditions, and its Nationwide Permits page lists the 2026 permits, including Maintenance and Bank Stabilization. Since March 15, 2026, submissions use the federal forms. A non-commercial permit costs $10, and no fee is charged for activities under a general permit.

What a general permit does not cover

The signed permit says other structures on the plans, such as docks, cantilevered decks, boat lifts and floats, that are not lawfully existing "will not be validated or 'legalized'" by it. It also makes the permittee responsible for obtaining any other permits and approvals. DEC's tidal wetlands page adds that work on a structure "so deteriorated that it is no longer functional, is not exempt from permit requirements," and that unpermitted work can bring fines or an order to remove structures.

Questions for the paperwork

A buyer can ask the seller whether the bulkhead, dock, deck or lift was built or replaced under a Village permit, a DEC authorization or a Corps permit, and ask for copies. A seller can gather those papers early. For the yard behind a bulkhead, Save The Great South Bay lists Bay Friendly Yards resources on native plants and invasive species.

Lindenhurst in our work

Lindenhurst is one of the towns we work, along with Commack.

Related pages

Thinking of selling? Read the Lindenhurst Seller's Guide.

Questions about Lindenhurst

Does a Lindenhurst bulkhead replacement need a Village permit?

The Village code says that before construction or alteration of any structure, including waterfront structures, the owner submits an application to the Building Inspector. The Village's permit requirements sheet lists a survey, plans, photographs and a $25 non-refundable filing fee.

Does DEC regulate bulkheads on Lindenhurst canals?

DEC's tidal wetlands program lists bulkheads, sea walls, retaining walls, rip-rap and gabions among the structures it regulates, and says its adjacent areas extend up to 300 feet inland from the wetland boundary.

What is DEC general permit GP-1-22-001?

It is a general permit effective October 25, 2022 for replacing functional and lawfully existing bulkheads in Nassau and Suffolk counties, either in place or landward, with limited re-sheathing, a height increase and limited maintenance dredging. DEC says no work is authorized until the signed Project Authorization is received.

What does a DEC bulkhead authorization request include?

DEC lists a site location map, project plans with a survey that depicts the existing bulkhead, three color photographs showing the time and date, and the Permission to Inspect Property form.

Does the Army Corps of Engineers permit bulkheads?

The Corps says Section 10 of the Rivers and Harbors Act requires a permit for work or structures in, over or under navigable waters, which typically include tidal waters. DEC notes a Corps permit may be required whether or not DEC requires one.

Does the general permit legalize an unpermitted dock or deck?

No. The signed permit says docks, cantilevered decks, boat lifts and floats that are not lawfully existing will not be validated or legalized by the permit.

What happens if bulkhead work starts without permits?

DEC says failure to obtain required permits before starting work subjects the owner and contractors to enforcement, which can include fines and an order to remove structures. The Village's permit sheet says the fee is doubled for legalizing existing structures.

What can a buyer ask a seller about a canal bulkhead?

A buyer can ask whether the bulkhead, dock, deck or boat lift was built or replaced under a Village building permit, a DEC authorization or a Corps permit, and ask for copies of each.

Sources

  1. https://ecode360.com/5119247
  2. https://villageoflindenhurstny.gov/wp-content/uploads/2025/08/Building-Permit-2025.pdf
  3. https://ecode360.com/14970111
  4. https://dec.ny.gov/regulatory/permits-licenses/general-permits/bulkhead-removal-and-replacement
  5. https://extapps.dec.ny.gov/docs/regions_pdf/gp122001signed.pdf
  6. https://dec.ny.gov/regulatory/permits-licenses/waterways-coastlines-wetlands/tidal-wetlands-permit-program/do-i-need-a-permit
  7. https://www.nan.usace.army.mil/Missions/Regulatory/Obtaining-a-Permit/
  8. https://www.nan.usace.army.mil/Missions/Regulatory/Nationwide-Permits/
  9. https://www.townofbabylonny.gov/FAQ.aspx?QID=329
  10. https://savethegreatsouthbay.org/take-action/bay-friendly-yards-resources/

More about Lindenhurst

Get market updates from Danielle and Kim

Danielle and Kim will send occasional updates. You can stop them any time.

Privacy

Danielle Sandella and Kim Fontanez Talk to Danielle and Kim